When a builder changes pipework as part of an extension, the drawing the homeowner keeps may show a different route from the one in the ground. In this anonymised account, a homeowner asked us to inspect work involving a shared sewer. Our survey identified concerns about the bends and the lack of access. Those are practical issues to raise while the builder can still compare the installation with the agreed drawings.

What the first survey was able to show
Jamie Ruby, the Cofton DJS engineer who attended, flagged two findings: bends that he considered unsuitable and missing access to the shared pipework. Both mattered to the homeowner because the sewer had to remain usable after the extension was finished. The concern with a bend depends on where it is, what it connects to and what access exists for future cleaning or inspection. The camera gives a view from inside the pipe. Whoever is comparing the installed work with the design still needs to know where that view was taken and which part of the drawings applies.
For a homeowner, the useful output is a finding that can be passed to the builder and acted on. Ask for the run reference, the direction of inspection and any footage that helps show the issue. If future access is in doubt, identify where it was expected on the drawing and ask how a contractor would reach the line in practice. A change can matter long after the work is finished, particularly if a shared line needs an urgent clearance.

Why access mattered alongside the bends
Think about the next visit to clear a blockage. The engineer needs a way to reach the shared pipe with cleaning equipment and a way to tell how far along the line it has travelled. A change of direction can make it harder to reach the next section from the same chamber. If the access point originally shown on the plan is missing, the engineer may have to work from a different chamber, if there is a suitable one. Once a floor or footing is in place, restoring access can mean disturbing work that has already been paid for.
A drawing describes the route the design envisages. The footage shows the inside of the reachable pipework at the time of the visit. If there is a difference, ask the surveyor to mark where the camera entered, how far it travelled and which part of the plan the finding relates to. That lets the homeowner and builder discuss a specific section. It also makes it possible to say where the camera could not reach, which matters if the owner is relying on the survey to answer a question about the whole run.
The angles and precise correction on this job are unpublished. For your own extension, ask the designer and sewerage company to check a proposed bend or access point against the requirements for that layout. The position relative to the extension footprint is particularly important. A detail that works outside the footprint may be unsuitable beneath it.
The correction and return visit
The homeowner took our findings to the builder. The builder corrected work that had departed from the original plans and covered the cost of the correction. Cofton DJS then surveyed the affected pipework again for Severn Trent. The water company’s final decision remains unconfirmed.
In this case the original plans gave both parties something concrete to refer to. When reporting a discrepancy on your own job, send the survey reference and the relevant drawing revision together. Ask the builder to identify the section they intend to change and explain what access it will leave once the work is finished. A written description is especially useful if the follow-up surveyor is coming to the site for the first time or the work spans more than one visit.
A return visit is an opportunity to check the same issue with the revised arrangement in place. The record should make it possible to see which run was inspected and whether the relevant section could be reached. Where later work will cover the route, keep the dated drawings and footage together. This makes it easier to tell what was intended, what changed and which part was seen before the ground or paving was reinstated.

If your own extension is near a shared sewer
Check the Severn Trent guidance on building over or near a sewer before work begins. Its process can require drawings and CCTV evidence depending on the asset and proposal. The accompanying building-over FAQ explains constraints relating to changes in direction and access within the footprint. Ask which conditions apply to your particular plans, and raise proposed changes before the contractor installs them.
For a post-work inspection, have the earlier survey and the relevant plans to hand. Confirm which lengths of pipe the follow-up needs to cover, whether the access points are available and who should receive the report. If relevant work is still exposed, ask the designer or water company what evidence they need before covering it. Photos taken while a pipe is visible can show where works were carried out. The camera footage answers a different question about the condition inside the pipe and what the survey could reach.
Tell our CCTV drain survey team where the extension sits, what information you already have and what the engineer is being asked to record. If a builder or sewerage provider specified the survey scope, share that before booking. Our build-over agreements guide explains how the survey fits into the wider application process.

Does the return survey settle whether the work is approved?
The return survey records what could be inspected after the correction. The sewerage provider decides whether the documents and installation meet the requirements for the particular project. Keep the email or decision letter with your survey and ask for clarification if any condition is still open. In this case, the follow-up inspection is the last step that Cofton DJS can describe from the information available.
Is a sewer map enough to decide where the extension can go?
A map is a useful starting point for identifying a public sewer. Severn Trent explains that some shared sewers will be missing from its records, and a line on a map may be approximate. If the proposed foundations are close to a suspected run, discuss how to confirm its route and depth with your designer and the sewerage company before the plans are settled. Let the surveyor know which section affects the design and ask them to distinguish between a located route and a section that could only be inferred.